Daily Report 2010-3-27 |
 |
| Date: 27.Mar.10 Sat |
Temperature: |
Min: |
Max: |
Daily Report
|
Ministry of Fishery CES NASICO |
| Weather Condition: Sunny & Calm: Wavy |
|
Procurement
|
|
Stone Material (ton)
|
1-1000 kg
|
200-500 kg
|
300-600 kg
|
400-800 kg
|
1-3 ton
|
2-5 ton
|
1-200 kg
|
Armour 1.4
|
Armour 1.75
|
Armour 2.4
|
Total
|
|
|
Daily
|
1204.92
|
57.26
|
286.76
|
|
133.12
|
|
58.82
|
40
|
10
|
9
|
59
|
|
|
Cumulative
|
238869.7
|
37970.02
|
9204.01
|
9591.05
|
52363.11
|
34150.9
|
48761.84
|
1726
|
395
|
270
|
2391
|
|
|
Quay wall
|
Fishery
|
Concerte Volume :
|
m3
|
Segment Name :
|
|
|
ROP
|
Concerte Volume :
|
m3
|
Segment Name :
|
|
|
Execution
|
|
Break Water
|
Weight (ton)Chainage
|
1-200 kg
|
200-500 kg
|
300-600 kg
|
400-800 kg
|
1-3 ton
|
2-5 ton
|
1-1000 kg
|
Armour 1.4
|
Armour 1.75
|
Armour 2.4
|
|
|
West
|
0
|
0
|
0
|
0
|
0
|
510
|
0
|
|
|
|
|
|
|
|
|
|
|
0+300-0+320
|
|
|
|
|
|
|
East
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
|
|
|
|
|
|
|
|
|
0+430-0+440
|
|
|
|
|
|
|
|
Temporary Dyke
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Reclamation Bund
|
---
|
|
|
|
|
|
|
|
|
|
|
|
|
Quay wall
|
Fishery
|
Concerte Volume :
|
m3
|
Segment Name :
|
|
|
ROP
|
|
m3
|
Segment Name :
|
|
|
Dredging & Reclamation
|
Dredging
|
Volume :
|
m3
|
Transporation : m3/ Km
|
|
Reclamation
|
Volume :
|
m3
|
Transporation : m3/ Km
|
|
Machinery
|
| |
Dozer D155
|
Loader wa470
|
Exe.pc300
|
Exe.pc400
|
Forklift
|
Truck 8 cum
|
Tru.16 cum
|
Tru.48 cum
|
Crane 100t
|
Cra.25 ton
|
|
Cra.35 ton
|
Gen. 250
|
|
Active at Site
|
|
3
|
3
|
2
|
|
1
|
1
|
2
|
1
|
1
|
|
1
|
|
| Active at Quarries |
|
9
|
11
|
10
|
|
|
|
38
|
|
|
|
|
5
|
|
Ready to Work
|
|
|
|
|
|
|
|
|
|
1
|
|
|
3
|
|
Under Repair
|
|
|
|
|
|
1
|
1
|
|
|
|
|
|
|
| |
Port. Welder
|
Air Comp
|
Pick up
|
Pajero
|
Land Cruiser
|
Port. light
|
High Washer
|
Excavator PC-300
|
Engineer's Lunch
|
Rental cars
|
Rock Breaker
|
Drilling Rigs
|
Grading Screen
|
| Active at Site |
2
|
2
|
4
|
1
|
|
|
1
|
|
|
5
|
|
|
|
|
Active at Quarries
|
|
|
|
|
|
|
|
|
|
|
6
|
10
|
1
|
|
Ready to Work
|
|
|
|
|
|
3
|
|
|
|
|
|
|
|
|
Under Repair
|
|
1
|
|
|
1
|
3
|
|
|
|
|
|
|
|
|
No. of Personnel
|
|
Management
|
Technical office
|
Implementation Work
|
Machineries & Equipment
|
HSE & QA
|
Financial/Administrative
|
Others
|
Total
|
|
1
|
4
|
10
|
85
|
1
|
3
|
34
|
138
|
| Events |
| متن مورد نظر |
| Site Visit / Meeting / Comments |
| متن مورد نظر |
| Problems & Obstructions |
| متن مورد نظر |
| Prepared by : |
Eng. Fatemian |
Approved by : |
Dr. Saffari |
|
|